Impact Type Map Description Start End
Parking/Traffic/Noise (ShowMap) Parking Lot #23 will remain closed through completion of the Physical Sciences, Phase II Project July 2007 March 2009
Construction/Parking (ShowMap) Lot # 57 will be closed for construction of the new student recreation center and ESPERS facility. October
2006
November 2008
Construction /
Parking / Noise
(ShowMap) Health & Physical Education / Field House building will close for the construction of the New Recreation Center and ESPERS Facility July 2006 November 2008
Construction /
Parking / Noise
Parking Lot #27, except for that portion immediately across from the Diehn Fine & Performing Arts Building will be closed until completion of the 3rd, 4th and 5th buildings of the Quad Student Housing Project July 2007 July 2009
Parking/Traffic/Noise (ShowMap) 48th Street will be closed to pedestrian and vehicular traffic until completion of the new Recreation Center March 2008 November 2008
Parking/Traffic/Noise (ShowMap) Parker Avenue will be closed to all non-construction vehicular traffic until completion of the last building currently under construction in the Quad Student Housing area March 2008 July  2009
Construction /
Parking / Noise
Parking Lot #7 and Bluestone Avenue from 49th Street to Melrose Parkway will be closed until completion of the Foreman Field project December
2007
July  2009
Construction / Noise Construction of the Powhatan Sports Complex July 2007 July  2008