Oceanography

Construction Start

Status

Contract awarded March 2014

  • Site work and Exterior Piping May 12-June 30
  • Cooling Tower Installation May 12-May 30
  • Interior Pipe Installation May 27-August 29
  • Trenching across Elkhorn June 2-June 20 (traffic will be reduced to one lane)

Construction Start

May 2014

Construction Completion

June 2015

Description

Replaces rooftop mechanical equipment with new air handlers and exhaust fans. Connects facility to central chiller plant.

Location

Elkhorn Avenue

Project Cost

Approximately $4M

Funding Source

State and University funding

Architect

DJG, Inc.

Contractor

Comfort Systems of Virginia

Delivery Method

2-Step IFB